For AI agents: read the machine-readable documentation index at /llms.txt or the single-file full reference at /llms-full.txt.

§ 21-236 — Interruptible standby electric service

Code of General Ordinances of the City of Tallahassee, Florida (Supp. No. 75: codified through Ordinance No. 25-O-28, enacted December 10, 2025) · Tallahassee City Code § 21-236

Corpus is an independent public-information project, not the official City of Tallahassee website. Stable reference: corpuslaw.us/code/2631a94f-f29a-4e95-bed5-05b09e1335f9

Sec. 21-236. - Interruptible standby electric service.

(a) Charges and collection. The city shall charge and collect for electric standby service on the basis of availability, application, character of service, limitation of service, monthly rate, definitions, determination of supplemental and standby service, specified capacity, and special provisions. (b) Availability. The interruptible standby electric service schedule is available throughout the entire territory served by the city. (c) Application. The interruptible standby electric service schedule (i) is applicable to customers whose electric requirements are normally supplied all or in part from on-site generating facilities and where the customer enters into the appropriate agreements with the city, and (ii) is required of any customer having on-site generation greater than 100 kW which supplies at least 20 percent of his total electrical load (excluding customers whose generators do not operate in parallel with the city's electric system) and who requests standby service. (d) Character of service. Service under the interruptible standby electric service schedule shall be single-phase or three-phase, 60-hertz, alternating current at standard available primary voltage. (e) Limitation of service. (1) Resale service is not permitted under this rate schedule. (2) Interruptible service under this rate schedule is subject to interruption during any time period that electric power and energy delivered hereunder from the city's available power supply resources is required to maintain service to the city's noninterruptible power customers. The city will not make additional off-system purchases during such periods to maintain service to interruptible loads except under the conditions set forth in Special Provision No. 7 of this rate schedule. (f) Definitions. The following words, terms and phrases, when used in this section, shall have the meanings ascribed to them in this section, except where the context clearly indicates a different meaning: Backup service means electric energy or capacity supplied by the city to replace energy or capacity ordinarily generated by a customer's own generation equipment during an unscheduled outage of the customer's generation. Maintenance service means electric energy or capacity supplied by the city to replace energy or capacity ordinarily generated by a customer's own generation equipment during a scheduled outage of the customer's generation. Otherwise applicable rate schedule means the existing rate schedule under which the customer would have received service if the customer had no self-generation. Standby electric service refers to backup or maintenance service or both. Supplemental service means electric energy or capacity supplied by the city in addition to energy and capacity which is normally provided by the customer's own generation equipment. (g) Determination of supplemental service requirements. A determination of the customer's supplemental power use shall be made for each 30-minute time interval of the billing period as follows: (1) During periods of non-outages of the customer's generation, all supply from the city is considered supplemental power. (2) During periods of unscheduled or scheduled outages of the customer's generation, the supplemental power amount shall be the amount of total city-supplied power in kW less the amount of standby power in kW as determined in determination of standby service requirements. (h) Determination of standby (backup and maintenance) service requirements. (1) In addition to other customer-provided information, the customer shall provide the city within three days of the end of the billing period the following information for each 30-minute time interval of occurrence of an unscheduled or scheduled outage of the customer's generation: a. Amount of load in kW ordinarily supplied by the customer's generation. b. Amount of load reduction in kW, if any, as a direct result of the customer's generation outage. (2) For each 30-minute time interval of occurrence of an unscheduled or scheduled outage of the customer's generation, the standby power amount shall be determined in accordance with the following formula. Standby power in kW shall equal: a. The amount of load in kW ordinarily supplied by the customer's generation; minus b. The customer generation output in kW; minus c. The amount of load reduction in kW, if any, as a direct result of customer's generation outage. In no event shall standby power amount be less than zero. (3) For each 30-minute interval of non-outages of the customer's generation, the standby power is zero amount. (i) Determination of specified standby capacity. (1) The customer and the city shall mutually agree upon a maximum amount of standby capacity in kW to be supplied by the city. This shall be termed for billing purposes as the specified standby capacity. (2) Whenever the specified standby capacity is exceeded by the creation of a greater actual standby power requirement in any 30-minute time interval of the billing period, then such greater demand becomes the new specified standby capacity. (3) When a change in the customer's standby capacity requirements occurs, the city and the customer shall establish a new specified standby capacity. (j) Monthly rate. The total charge will be the sum of amounts calculated in subsections (j)(1), (2), and (3) of this section and, if applicable, as provided for under the special provisions in subsection (k) of this section. (1) Customer charge: $291.12 (2) Supplemental service charges. All supplemental power requirements shall be billed in accordance with the charges for service of the otherwise applicable rate schedule. (3) Standby service charges. Standby service charges will be the sum of amounts calculated in subsections (j)(3)a.—g. of this section: a. Local transmission and distribution capacity: $4.53 per kW times the specified standby capacity adjustment for power factor, less delivery voltage discount as described in subsection (g)(3)e. of this section, if applicable. b. Generation and bulk transmission capacity. The charge shall be the greater of: 1. $0.48 per kW times the specified standby capacity; or 2. $0.23 times the sum of the daily maximum 30-minute kW demand of actual standby use occurring during the billing period. c. Energy charge (non-fuel): $0.00324 for all kWh per billing period. d. Fuel charge. The fuel charge shall be calculated as follows: 1. For energy supplied by the city during the billing period, the fuel charge shall be based on the energy delivered at the city's point of interconnection expressed in kWh and shall include the city's fuel cost which will be equal to the average system fuel and purchased energy expenses adjusted for losses as determined by the city. 2. To minimize interruptions, the customer may elect to have the city attempt to purchase energy from other electric systems. If the city is successful in purchasing such energy, the customer will pay the additional cost, including, but not limited to, costs associated with losses and transmission (expressed in mills per kWh) incurred by the city as the result of such purchase, plus a charge of three mills per kWh delivered to the customer. e. Delivery voltage discount. The charge for local transmission and distribution capacity set forth in subsection (j)(3)a. of this section shall be subject to a discount of $1.52 per kW of specified standby capacity. This discount is available only if service is provided and metered at transmission voltages of 115,000 volts, the city has such service available in the immediate area of the load, the customer owns and maintains the necessary transformation equipment, and the customer requesting service agrees to pay a minimum billing demand of 10,000 kW per month. The city reserves the right to determine the feasibility of providing the service at 115,000 volts or greater. f. Power factor adjustment. For customers with metered demands of 500 kW or more for three or more months out of the 12 consecutive months ending with the September billing of each year, the total monthly charges for each of the following consecutive 12 months will be increased by $0.31 for each kVAr by which the reactive demand numerically exceeds 0.62 times the metered kW demand or will be decreased by $0.31 for each kVAr by which the reactive demand is numerically less than 0.62 times the metered kW demand. g. Tax adjustment. The amount computed at the monthly rate in this section shall be subject to taxes, assessments, and surcharges imposed by any governmental authority, which are assessed on the basis of meters or customers or the price of revenues from electric energy or service sold or volume generated or purchased for sale or sold. (k) Special provisions. (1) The city will make reasonable provisions to ensure satisfactory and continuous service, but does not guarantee a continuous supply of electrical energy and shall not be liable for damage occasioned by interruptions of service or failure to commence delivery caused by an act of God, or the public enemy, or for any cause reasonably beyond its control, including, but not limited to, the failure or breakdown of generating or transmitting facilities, floods, fire, strikes or action or order of any agency having jurisdiction in the premises, or for interruptions which are necessary for inspection, repair or changes in the generating equipment or transmission and distribution system of the city. (2) The customer shall notify the city immediately of any defect, trouble or accident which may in any way affect the delivery of power by the city to the customer. (3) The city will, under the provisions of this rate, require the customer to enter into a contract with the city setting forth specific terms and conditions of implementing this and other rate schedules. Whenever the customer increases his electrical load, which increase requires the city to increase facilities installed for the specific use of the customer, a new term of service may be required. (4) Customers taking service under this rate schedule who desire to transfer to firm full requirements service will be required to give the city written notice at least 60 months prior to such transfer. (5) Customers taking service under this rate schedule who desire to transfer to this rate schedule will be accepted by the city on a first-come, first-served basis. The amount and the duration of the availability of interruptible service under this rate schedule shall be determined from time to time exclusively by the city. Nothing in this section shall require the city to acquire new generating or power supply resources to supply interruptible service under this rate schedule. (6) Special equipment needed to provide interruptible service will be installed subject to availability. Service under this rate schedule shall commence with the first complete billing period following the date of equipment installation. (7) To minimize the frequency and duration of interruptions hereunder, the city will attempt to purchase power and energy from other sources during periods of normal interruption. If such energy can be purchased, customers receiving service under this rate schedule will be notified. If and when the city is successful in making such purchases, the customer agrees to pay, in lieu of the normal energy charges (including fuel charges) provided hereunder, the actual additional cost incurred by the city for such purchases plus three mills per kWh. The cost of such purchased energy shall be based on the average cost of all purchased energy provided under this rate schedule. Customers may avoid these higher charges by terminating their use of electricity during such periods. (8) The city will furnish service under this rate schedule at a single voltage. Equipment to supply additional voltages or additional facilities for the use of the customer shall be furnished and maintained by the customer. The customer may request the city to furnish such additional equipment; and the city, at its sole option, may furnish, install and maintain such additional equipment and will charge the customer for the use thereof. (9) The customer shall allow the city to install time recording metering on the electrical output of all customer-owned generation equipment. The metering location must be accessible to city personnel for testing, inspection, maintenance and retrieval of recording generation output data. The customer shall reimburse the city for the installed cost of the metering and be charged an amount per month to be determined by the city for operation and maintenance of the equipment by the city. (10) Metering of customer generation shall not be required for customers whose requirements from the city are either totally standby or totally supplemental. (11) In the event the customer does not provide outage information to the city within three days of the end of the billing period, the city shall render a bill based on all city-supplied power being supplemental service. If the customer provides outage information for the current billing period prior to the end of the next billing period, the city shall issue a revised bill and assess the customer an additional $200.00 charge. (12) The customer should maintain accurate generation performance records available for review by the city for verifying outage information utilized in the billing procedure. The customer shall cooperate with the city in providing additional information the city deems necessary to validate appropriate billing determinations. (13) If the actual maximum 30-minute standby power supplied by the city exceeds the specified standby capacity, the customer shall be billed on the excess amount for previous billings rendered up to 12 months under the rate schedule for (i) local transmission and distribution capacity and (ii) generation and bulk transmission capacity, at a rate of 125 percent of the corresponding standby service charges. (14) Where primary service of 12,470/7,200 volts is requested from the city's underground network system, such service will be provided only where the customer installs dual primary circuits complete with automatic load transfer equipment. Where more than one meter is utilized for this service, each shall be computed separately for billing purposes, unless installed by the city for reliability and/or capacity requirements.

(Code 1984, § 25-40; Ord. No. 87-O-0107, § 2, 8-19-1987; Ord. No. 92-O-0017AA, § 14, 7-7-1992; Ord. No. 93-O-0019AA, § 9, 7-13-1993; Ord. No. 94-O-0028, § 11, 7-6-1994; Ord. No. 95-O-0041, § 9, 11-21-1995; Ord. No. 96-O-0035, § 9, 12-18-1996; Ord. No. 01-O-10AA, § 9, 3-21-2001; Ord. No. 06-O-23AA, § 8, 3-29-2006; Ord. No. 13-O-07, § 9, 3-27-2013; Ord. No. 14-O-42, § 9, 10-22-2014; Ord. No. 18-O-27, § 9, 9-26-2018)

Ask a question about Tallahassee law

Corpus searches the Tallahassee sections it holds and shows the ones that match, with their citations. Free, no sign-in.