§ 62-82 — Standards for oversizing Concord Utilities extensions
Code of Ordinances, City of Concord, North Carolina (Supp. 53 Update 2: codified through Ordinance No. 26-83, enacted August 13, 2026 (online updated September 15, 2026)) · Concord Code of Ordinances § 62-82
Corpus is an independent public-information project, not the official City of Concord website. Stable reference: corpuslaw.us/code/306684af-02b9-4b18-9322-f2ac1e73c19a
Sec. 62-82. - Standards for oversizing Concord Utilities extensions.
(a) Subject to city council approval as provided in sections 62-80 and 62-81, the city shall allow extensions within new developments upon the request of the developer or property owner. The responsibility for and cost of such extensions shall be borne by the requesting party, except as provided below. (1) If city planning documents and engineering calculations demonstrate that a larger capacity extension or modification to the Concord Utilities will be needed to serve the surrounding area, the city may elect to require the owner or developer to design and install larger diameter pipes than those required to serve the subdivision or private development. The owner or developer shall request and receive bids from at least three contractors for the installation and materials required to serve the subdivision or private development with water and wastewater collection and bid the pipe sizes requested by the city as an alternate. If the city elects to require the developer to up-size pipe diameters to accommodate future Concord Utilities service demands, the city may pay the developer in an amount, as negotiated between the city and owner or developer, based on the difference between the base bid and the alternate bid. Any reimbursement shall be by developer contract. Such developer contract shall be written to provide an equitable distribution of the cost of improvements to the city's system(s) consistent with the policies and fees established in this chapter, or other ordinance(s) and in consideration of the relative burden placed upon the system by the proposed development, the extent to which other city customers may benefit from the improvement, the extent to which fees maybe or have been paid by others for future improvements, the requirements of section 62-12 and other relevant factors. (2) The total amount to be reimbursed to the developer, owner, or subdivider by the city under this section shall not exceed the costs incurred by the developer, owner, or subdivider in constructing the extension(s). (3) The terms and conditions of any reimbursement or financial participation by the city pursuant to this article shall be set forth in a written contract between the city and the developer or property owner for which the extension is to be constructed. Failure to reach a reasonable cost for any oversizing size may result in the denial of the extension.
(Ord. No. 04-17, § 1, 3-11-2004; Ord. No. 07-11, § 7, 2-8-2007)