Section IX — Erosion and sedimentation control

Code of Ordinances of the City of Edmond, Oklahoma (Codified through Ordinance No. 4097, enacted August 10, 2026 (Supp. No. 40)) · Edmond Code of Ordinances tit. 23, App. - Standard Drainage Policy, Section IX

Corpus is an independent public-information project, not the official City of Edmond website. Stable reference: corpuslaw.us/code/4b962462-1490-49e3-966a-b9cfa4db249c

Section IX. - Erosion and sedimentation control.

PURPOSE. The purpose of this section is to provide guidance in the design of effective management of erosion and sedimentation and to protect water quality and the general health, safety, and welfare of the residents of the City of Edmond. GENERAL REQUIREMENTS (A) Development activity shall not be conducted unless appropriate erosion and sedimentation facilities are designed, installed, and maintained throughout the life of the development. (B) All erosion and sediment control methods shall be indicated on the final construction and/or building permit plans. (C) All earth slopes and earth areas, new or existing, subject to erosion, such as adjacent to trickle channels, inlet structures, and outlet structures, within any area designated for detention or drainage shall be solid slab sodded with Bermuda grass sod from a local source or have permanent established growth of vegetation. All vegetation areas shall be fertilized, watered, and in an established growing condition with permanent vegetation prior to completion or acceptance of any stormwater drainage facility, and/or development. DESIGN CONSIDERATIONS (A) General Design Principals. Practical combinations of the following principles shall be utilized, as a minimum, in planning measures to be installed for any land disturbing activity. (1) The land disturbing activity shall conform to existing topography and soil type so as to create the lowest practicable erosion potential. (2) The disturbed area and the duration of exposure of bare earth to erosive elements shall be kept to a practicable minimum through construction scheduling and management. (3) Cut and fill operations should be kept to a minimum. (4) Disturbed soil shall be stabilized as quickly as practicable. (5) Natural vegetation shall be retained, protected, and supplemented whenever feasible. (6) Temporary vegetation or mulching shall be employed in a timely manner to protect exposed critical areas during development. (7) Permanent vegetation and structural erosion control measures shall be installed prior to final acceptance of developments or as soon as seasonal planting restrictions allow. (B) General Practice: Soil and water conservation measures include but are not necessarily restricted to vegetation, mulches, sediment basins, dikes, grade stabilization structures, sediment traps, land grading, diversions, waterways or outlets, and riprap. Vegetative practices shall be applied to control erosion. The practice can be either temporary and/or permanent depending on the site specific needs. EROSION AND SEDIMENT CONTROL CRITERIA (A) Long term permanent vegetative cover obtained through seeding, mulching, sprigging, sodding, or planting using acceptable varieties such as Bermuda grass, Kentucky 31 Tall Fescue, or Weeping Lovegrass shall be used to control erosion on a permanent basis. (B) Short term vegetative cover through seeding or mulching using small grains like oats, rye and wheat, and sundans and sorghums, shall be used to control immediate erosion. This practice may be effective for areas where soil is left exposed for a period of 6 to 12 months and shall not be deemed permanent erosion control. Straw bale dikes may be utilized where no other practice such as silt dikes or silt fences are feasible. This temporary barrier with a life expectancy of three months or less can be installed across or at the toe of a slope for the contributing drainage areas in accordance with the adopted standards. Hay and sod mulching, as a temporary measure, may be used for embankment stabilization in areas where surface runoff is to be directed down a slope. Erosion matting shall be used for channel embankment and slope stabilization where a permanent erosion control cover has not been established prior to use. The specified material shall be installed as recommended by the manufacturer of the proposed material. (C) A coarse rock stabilized construction entrance underlain with stabilizing fabric shall be built in accordance with the adopted standards to reduce or eliminate the tracking or flowing of sediment onto the public right-of-way. (D) A concrete or stone outlet structure shall be constructed in areas where the entire drainage area to the structure is not stabilized or where there is a need to dispose runoff at a protected outlet or where concentrated flow for the duration of the period of construction needs to be diffused. (E) A grade stabilization structure in the form of a paved chute or flume shall be constructed to prevent erosion where concentrated flow of surface runoff is to be conveyed down a slope of 3% or greater. (F) Stormwater detention facilities may be used temporarily as sediment basins. A temporary outlet structure for the stormwater detention facility to work as a sediment pond shall be constructed. At the end of the construction activity, the developer shall remove all collected sediment from the detention facility and outlet structure and restore / construct the facility to the approved detention design plans. The technologies and methodologies associated with erosion and sediment control are continually being developed and modified. For the current Be Management Practices suggested for use, refer to the U.S. Environmental Protection Agency website as well as recent publications by trade organizations and others.

Ask a question about Edmond law

Corpus searches the Edmond sections it holds and shows the ones that match, with their citations. Free, no sign-in.