Section I — General drainage policy for the City of Edmond

Code of Ordinances of the City of Edmond, Oklahoma (Codified through Ordinance No. 4097, enacted August 10, 2026 (Supp. No. 40)) · Edmond Code of Ordinances tit. 23, App. - Standard Drainage Policy, Section I

Corpus is an independent public-information project, not the official City of Edmond website. Stable reference: corpuslaw.us/code/c5aa17d3-0a65-454c-bcc9-9200bafdeab3

Section I. - General drainage policy for the City of Edmond.

GOAL: It is the goal of this policy to establish minimally acceptable standards to be utilized in the design of stormwater drainage system improvements and where required by sections herein limit stormwater runoff rates after development to their historic value. PURPOSE: The purpose of this Drainage Standard STD-4 00 is to establish standard practices for the design and construction of stormwater drainage systems within the City of Edmond. The design factors, formulas, graphs, and procedures are intended for use as a minimum standard in the design of stormwater drainage systems. Methods of design other than those indicated herein should be considered where professional experience clearly indicates the minimum requirements as listed herein will not provide the level of service or the level of protection intended. However, there should be no extensive variations from the practices established herein without the express approval of the City Engineer. Performance Requirements: The overall goal of these standards is to provide guidance in the design, construction, operation, and maintenance of drainage system improvements. As such, an adequate drainage system could be designed, approved by the City, and installed according to plan. However, if the proposed improvements do not function as intended by these standards, the site may be in violation of this standard. Therefore, the specific goal is not standards and specifications for practice, but the mandate that the improvements must function as intended. If additional control structures or improvements are needed to ensure total compliance with this standard, the design must be revised and approved, and the new measures shall be installed. MINIMUM SURFACE DRAINAGE REQUIREMENTS FOR THE CITY OF EDMOND (A) General Design criteria: (1) Drainage facilities shall be designed to provide a sufficient stormwater drainage system for the conveyance of stormwater runoff received from upstream and from the subject property with due allowance having been made for continued conveyance of stormwater runoff from adjacent properties as the drainage basin develops. The drainage system including streets, bridges, culverts, open channels, detention/retention facilities, etc., shall be designed to carry all probable storm recurrence intervals up to and including the 100 year storm event. (2) A dedicated drainage easement shall encompass all land lying below the water surface elevation generated by the 100 year storm event and resulting stormwater runoff. These dedicated drainage easements shall be platted as Common Area in all developments. (3) Site improvement shall provide for the grading of all building pads to an elevation where the lowest finished floor elevations will not be subject to overflow from the 100 year storm event. In all developments, surface water from each dwelling lot will flow away from each dwelling in a controlled manner to an approved collection or disposal location as required under Section VII of this Standard. (4) Erosion and sedimentation control facilities with construction specifications and operation and maintenance procedures detailing all erosion and sedimentation control measures which are established and the required maintenance during the life of the development shall be provided. (5) No improvements shall be constructed which will increase the frequency or the depth of flooding. (B) Existing Drainage Structures: Existing structures within and adjoining a proposed development shall be evaluated in terms of hydraulic capacity and structural soundness. Those structures found to be structurally inadequate shall be modified or completely removed and replaced by the developer. Structures found to be hydraulically inadequate for flow and/or for protecting property as a result of the changing runoff characteristics shall be replaced or modified by the developer to provide the required capacity and/or protection. (C) Utilities: All utilities located within the floodplain or any other open channel or swale shall be designed to prevent infiltration of flood water and to protect against washouts. Location of the utilities shall not restrict flood flows. FLOODPLAIN DESIGNATIONS. Any reference to official floodplain maps shall mean the highest order of floodplain designation recognized by the City of Edmond. The City Engineer will maintain an up-to-date file of such designations. The highest available order of study shall be the basis of design unless it can be clearly shown that the subject study is in error. Contested studies shall be brought to the attention of the City Engineer. DRAINAGE PLAN PREPARATION (A) Preparations (1) Plan and profile shall be drawn on sheets 24" × 36" to a horizontal scale of 1" to 20' or 1" to 40' and vertical scale of 1" to 2' or 1" to 4* (except that scales may vary on special projects, such as culverts and channel cross sections. However, these exceptions must be clearly marked and explained on the Plan and Profile sheets). (2) Stationing shall proceed upstream with the North arrow pointing to the top of the sheet, or to the right. The 100 year storm event water surface elevations on all channels shall be provided with cross sections accompanied by base flood elevations. A stream profile shall also be provided to enable extrapolation of base flood elevations between the cross sections. (3) Plans for the proposed drainage system shall include property lines, lot and block numbers, dimensions, right-of-way and easement lines, floodplains, street names, paved surfaces (existing or proposed), contract limits, location, size and type of inlets, manholes, culverts, pipes, channels and related structures, outfall details, miscellaneous riprap placement, 2' contour lines, flow arrows, title block. (4) Profiles shall indicate the proposed system (size and material) with elevations, flowlines, gradients, left and right bank channel profiles, station numbers, inlets, manholes, ground line and curb line elevations, typical sections, riprap construction, filling details, open drainage features, pipe crossings, design flow capacities, and title block. (5) Official floodplain designations and delineations of the floodplains and floodways denoting limits of permissible developments shall be shown on all preliminary plans and final plats submitted for approval wherever such plans and plats contain a floodplain segment. In any case in which official floodplains are not delineated, they shall be determined on the basis of these standards and shall be shown on all preliminary plans and final plats submitted for approval. (6) The limits of the floodplains shown on regulatory floodplain maps are close approximations based on extrapolations made between widely-spaced cross sections. Therefore, the actual limits of the floodplain shall be determined by extracting base flood elevations from the stream profile and determining where each elevation intersects the adjacent existing topography. If a conflict exists between the overlay of the regulatory floodplain map and the existing topography, a submittal of a Letter of Map Amendment (LOMA) or Letter of Map Revision (LOMR) by the Developer/Owner to the Federal Emergency Management Agency (FEMA) is required when the FEMA Flood Insurance Rate Map (FIRM) conflicts with proposed lots or other proposed structures or improvements. (B) Submittals (1) Computations and plans to support all drainage designs shall be submitted to the City Engineer for review. The computations and plans shall be in such form as to provide the basis for timely and consistent review and will be made a part of the permanent record for future evaluation. The computations and plans shall be accompanied by the certification of a registered professional engineer licensed to practice in the State of Oklahoma. Before final acceptance, the submitting engineer shall provide an "as built" plan based on field survey data of the streets, stormsewer, detention facilities, and all other conveyances of stormwater; a revised set of drainage calculations that correspond with the "as-built" plans; and a letter of certification stating that the "as-built" site complies with all governing ordinances and adopted drainage standards of the City of Edmond.

Ask a question about Edmond law

Corpus searches the Edmond sections it holds and shows the ones that match, with their citations. Free, no sign-in.