§ 405.230 — Public Storm Sewers And Other Drainage Appurtenances

Code of Ordinances, City of O'Fallon, Missouri (Code 2026-10-22) · O'Fallon City Code § 405.230

Corpus is an independent public-information project, not the official City of O'Fallon website. Stable reference: corpuslaw.us/code/40e43b28-a6d8-426b-ae45-3b7bebe22ee5

Section 405.230: Public Storm Sewers And Other Drainage Appurtenances.

A. In addition to the installation of curbs or gutters along the streets as required by this Chapter, storm sewers shall be required. Such systems will be equipped with adequate basins, inlets and outlets and shall be constructed in accordance with the applicable provisions in the specifications. The stormwater drainage system shall be separate and independent of the sanitary sewer system. The plans and specifications for the disposing of stormwater shall be approved by the City Engineer and/or his/her designee. B. General. All construction details and specifications pertaining to stormwater drainage shall be in accordance with the Metropolitan St. Louis Sewer District (MSD) Standard Construction Specifications for Sewers and Drainage Facilities, latest version, and the City of O'Fallon's requirements, unless otherwise noted herein. A registered engineer's seal is required on all drainage plans submitted for approval. C. Design Criteria. Unless otherwise specified below or in other City of O'Fallon requirements, all engineering design shall adhere to the Metropolitan St. Louis Sewer District (MSD) Rules and Regulations and Engineering Design Requirements for Sanitary Sewer and Stormwater Drainage Facilities, latest revision. 1. Chapter 5 (Flood Plain Requirements) is not being adopted. For all floodplain requirements, see Chapter 415 of the City Code.[1] 2. All references to "District" in any form shall be replaced with "City of O'Fallon" where appropriate. 3. All stormwater design is to be by the Rational Method, except that in certain large developments, the use of other methods of analysis such as the Unit Hydrograph will be considered for stormwater design. However, prior approval must be obtained from the City Engineer and/or his/her designee at the preliminary design stage, where use of the Unit Hydrograph or other methods of analysis are requested. 4. Runoff factors shall be per the MSD requirements. D. Drainage Structures. All structures shall be designed for HS20-44 loading. 1. Bridges. Bridges shall be designed for the 100-year storm frequency and provide two (2) feet of freeboard between the bottom of superstructure and highwater elevations. 2. Culverts. a. Crossroad culverts, not at low points, shall be designed on a storm frequency of fifteen (15) years with entrance control and two (2) feet of freeboard at the shoulder line. b. Culverts, at or near low points in floodplains, shall be designed on a storm frequency of one hundred (100) years with entrance control and two (2) feet of freeboard at the shoulder line. c. Culverts, at or near low points not in floodplains, shall be designed on a storm frequency of fifty (50) years with entrance control and two (2) feet of freeboard at the shoulder line. 3. Roadways. Whenever a watercourse is proposed or exists within proximity of and is approximately parallel to an existing or proposed roadway, the low shoulder elevation of the roadway shall be established from the highwater elevation with one (1) foot of freeboard in non-floodplain areas and two (2) feet of freeboard in floodplain areas. 4. Street Inlets. In certain cases, where steep grades or other unusual conditions are encountered, a grated through may be required in lieu of multiple inlet structures upstream in order to eliminate excessive bypass. 5. Pipes. a. Pipes within the public right-of-way or easement shall be reinforced concrete pipe (RCP) ASTM C-76, Class III, and a minimum of twelve (12) inches diameter. Design calculations may be submitted allowing a lower class of RCP. b. The use of high-density polyethylene (HDPE) shall not be allowed. c. The use of polypropylene (PP) may be allowed when approved by the City Engineer. The use of PP shall follow ASTM guidelines and air and mandrel testing, per MSD specifications, shall be satisfactorily completed prior to both ninety percent (90%) and ten percent (10%) escrow releases. d. The use of corrugated steel pipe should only be considered when all options for reinforced concrete pipe are deemed not feasible. Corrugated steel shall be M-36, minimum sixteen-gauge asphalt polymer, or aluminized coating, a minimum of eighteen (18) CSP, will be allowed with these conditions. This pipe material may be used for private driveway culverts or private road culverts, as the maintenance shall be with the property owner, even though the pipe is in the right-of-way. e. Additional General Pipe Requirements. (1) The City Engineer and/or his/her designee shall review the proposed project for suitability. (2) Standard concrete drainage structures and flared end sections will be used in the installation process. (3) Installation shall be in accordance with ASTM D-2321 and/or manufacturer's recommendation, whichever is more stringent. f. The required stormwater hydraulics shall be submitted with all types of pipes. g. Pipe reduction will not be allowed. h. In situations where storm pipe cover is less than three (3) feet, calculations will be required to determine the class or gauge of pipe. i. All new concrete pipe shall be installed with O-ring rubber-type gaskets per MSD Standard Construction Specifications. Connections at all existing structures are to be made with rubber, watertight A-lock joints or approved equals, as determined in the preconstruction meeting or prior to construction. Broken and/or unsuitable connections shall be removed and replaced. j. Pipes normally should be sized using the partial flow design; however, under special circumstances, full flow design will be allowed, provided hydraulic grade line information is shown indicating adequate freeboard. This additional information will be supplied for the 15-year and 100-year storms. k. Freeboard requirements will be two (2) feet from the inlet sill or manhole top. l. Starting Hydraulic Grade Line. (1) If a pipe run drains into a detention basin, then the starting hydraulic grade shall be calculated for both the 15-year routed and the 100-year low-flow blocked highwater elevations of the basin. Freeboard requirements only apply to the 15-year calculations, however for the 100-year calculations, all of the water must remain within the structure. (2) If a pipe run drains into a naturally occurring creek, then the starting hydraulic grade shall be calculated from the hydraulic model of the creek for the 100-year highwater elevations of the creek. For studied creeks, use the effective Flood Insurance Study published by FEMA for that specific creek. For unstudied creeks, use the MSD method of determining the 100-year highwater elevations of the creek. m. If existing storm sewers are located near a proposed development, where proposed storm sewers are planned, then they shall all be connected, at the direction of the City Engineer. No new flared-end pipe sections shall be allowed to be placed within one hundred (100) feet of an existing flared-end pipe section, nor will a rip-rap area connection between pipes be allowed to be installed, unless the discharge separately into a creek. Instead, an enclosed connection shall be made between the two (2) pipe sections, the existing flared-end section shall be removed, area inlets or other means of drainage capture shall be installed as required, and the area shall be covered and regraded as needed to ensure that proper drainage for the area continues unabated. The developer responsible for the new connection shall be responsible for obtaining all required easements, performing piping installation, performing grading operations and any/all other work necessary to achieve this connection. E. Plans And Calculations. 1. General. Plans shall be any scale from one (1) inch equals ten (10) feet through one (1) inch equals one hundred (100) feet so long as the scale is an increment of ten (10) feet. Plans shall be prepared on exhibits nominally twenty-four (24) inches by thirty-six (36) inches. All calculations submitted shall be in accordance with Section 405.100 and shall include the following information: a. Site Drainage Map. A drainage map is required and should be developed from a base reproduction of the site plan or grading plan. Plans and calculation shall be prepared in accordance to the checklist pertinent for the type of development (See Title IV Notes: Notes and Appendixes, Appendix C[2] for application and checklist for compliance with this Section). b. Supplemental Drainage Map. A supplemental map may be required and should be developed from a portion of U.S.G.S. Quadrangie Map. This map must include the site boundary and the watershed tributary to the project area. c. Surface Drainage. The following information shall be provided by the developer: (1) No sheet flow over one (1) cfs will be allowed over terraces with slopes that are and/or greater than five (5) feet in height. Berms and/or swales shall be provided to collect the flow at the top of the terrace and carry it to a drainage structure. Total accumulation inside berm and/or swales shall be a maximum of three (3) cubic feet per second. (2) Excluding existing creeks and swales not being modified by the proposed development, the developer's engineer shall provide critical cross sections, profiles and hydraulic computations for ditches and swales with flows in excess of one (1) cfs and creeks with flows in excess of three (3) cfs. (3) Overland Flow Swale. All emergency/overland flow swales shall be designed on the plans. At all low points on streets, the flow-line elevation of the swale at the right-of-way line shall not exceed eight (8) inches higher than the top of the curb inlet (at said low point). The alternative to this depth is to install a larger storm pipe, capable of handling the 100-year, twenty-minute storm. d. Location Of Drainage Structures. The lateral location of all drainage structures shall be shown by street center line stationing and perpendicular offset distance, and in large lot subdivisions, by referencing to rear lot line, in addition to the following requirements: (1) Inlets shall be appropriately sized and spaced, taking into consideration by pass, depth of flow and width of spread of flow in gutters. (2) For inlets in vertical sag curves, the center of the main chambers shall be placed within one (1) foot of the exact mathematical low point. (3) All manholes shall be located outside of the proposed roadway pavements. (4) Inlets shall be located as follows: (a) Sump design shall be in accordance to the City of O'Fallon's adopted street standards. (b) Location of area inlets in roadway ditches shall be compatible with ultimate improvements at an elevation compatible with the shoulders and sidewalks. (c) No driveway shall be closer than six (6) feet from the edge of a curb inlet.

[R.O. 2008 § 405.230; Ord. No. 6496 , 9-13-2018 ; Ord. No. 7056 , 10-26-2023 ; Ord. No. 7196 , 3-27-2025 ]

Ask a question about O'Fallon law

Corpus searches the O'Fallon sections it holds and shows the ones that match, with their citations. Free, no sign-in.