§ 29-88 — Schedule GD (demand service)

Municipal Code of the City of Rock Hill, South Carolina (Codified through Ordinance No. 2026-49, adopted October 12, 2026. (Supp. No. 95, Update 1)) · Rock Hill Municipal Code § 29-88

Corpus is an independent public-information project, not the official City of Rock Hill website. Stable reference: corpuslaw.us/code/8a5fb784-fd57-4011-961e-e0bd6f2280e0

Sec. 29-88. - Schedule GD (demand service).

(a) Availability. Schedule GD service is available only to consumers with a metered demand of 30 kw to 750 kw, including commercial and industrial consumers, county buildings, schools, churches and other eleemosynary consumers, for lighting, cooking, heating, refrigeration, water heating and other power service supplies to the individual store, industry, commercial establishment or other qualified consumer through a single meter at one delivery point. (b) Character of service. The city will furnish 60 hertz, three-phase, 120/280 volts, four-wire, wye; or 277/480 volts, four-wire, wye. Where three-phase service is not available, it will be extended to the consumer's premises. (c) Limitation of service. (1) The following requirements shall be applicable to the use of electric motors. Motors of ten horsepower or larger which are frequently started shall be equipped with over-current protective devices in each phase conductor, and also be equipped with starting equipment set to a limit of 300 percent of full load current, or 65 percent of locked motor current value. Motors of ten horsepower and larger having intermittent or continuous duty shall be equipped with over-current protective devices in each phase conductor; they shall also be equipped with starting equipment set to a limit of 300 percent of full load current, except where served from a separate transformer installation and no other consumer is served from the same bank of transformers. (2) The obligation of the city in regard to supplying power is dependent upon its securing and retaining all necessary rights-of-way, privileges and permits for the delivery of such power, and the city shall not be liable to any consumer or applicant for power if it is delayed in or is prevented from furnishing power by its failure to secure and retain such rights-of-way, privileges and permits. (3) Standby or resale service is not permitted under this rate schedule. (d) Special conditions. (1) Before wiring any premises or purchasing equipment for any premises, the consumer shall give the city notice in writing of the location of the building, together with a list of the electrical devices to be used thereon, and shall ascertain the character of service available at such premises. The city shall specify the voltage and type of electrical service to be furnished, as well as the location of the meter and the point where the service connections shall be made. (2) Electric underground service lines or conduits may be permitted, but the installation and maintenance of such underground circuits will be at the expense of the consumer. (3) Temporary construction service may be supplied at whatever voltage is available, provided the applicant agrees to defray all installation and removal costs necessary to providing service, and to place on deposit with the city an amount equal to these costs before the work is undertaken. (4) An application and contract in writing shall be required, which when accepted by the proper officers of the city shall constitute the contract between the consumer and the city. No promises, agreements, statements or representations of any agent or employee of the city, or other person, shall be of any binding force or effect unless incorporated in writing in such contract. The contract shall not be transferable or assignable without written consent of the city. (5) On initial installations, the service agreement shall extend for a term adequate to reasonably amortize specific installation costs incurred by the city. Thereafter, the service agreement shall be renewable during such terms as shall reasonably enable the city to properly anticipate and meet the load requirements of the customer, with reasonable provision for termination, on adequate notice to the city. (e) Monthly rate. (1) Customer charge: $27.46/month. (2) Demand charge: First 30 kw of billing demand: $0.00 per kw. Over 30 kw of billing demand: $5.669 per kw. (3) Energy charge: For the first 125 kwh per kw of billing demand: First 3,000 kwh: 16.981 cents per kwh. All over 3,000 kwh: 11.409 cents per kwh. For the next 275 kwh per kw of billing demand: All kwh: 8.581 cents per kwh. For all over 400 kwh per kw of billing demand: All kwh: 7.378 cents per kwh. (f) Adjustment. The amount computed at the rate set out in subsection (e) of this section shall be adjusted plus or minus by an amount calculated in accordance with the formula specified in the city's purchased power cost adjustment clause, which is incorporated by reference as a part of this rate schedule. (g) Minimum charge. The monthly minimum charge shall be the customer charge plus the demand charge, if any. (h) Determination of billing demand. The demand for billing purposes each month shall be the maximum integrated 30-minute demand in the previous six months, including the month for which the bill is rendered, but not less than 50 percent of the contract or billing demand. Metering equipment necessary to provide hourly loan measurements and any other date reasonably required for the city to bill and otherwise account for service will be provided to the customer. (i) Power factor correction. When the monthly power factor of the consumer's power requirements is less than 85 percent, the billing demand in kilowatts will be corrected for that month by multiplying the billing demand by 85 percent and dividing same by the power factor for that month, expressed in percentages. (j) Interruption of service. (1) The city will make reasonable provisions to ensure satisfactory and continuous service, but does not guarantee a continuous supply of electrical energy and shall not be liable for damages occasioned by interruptions of service or failure to commence delivery caused by an act of God or the public enemy, or for any cause reasonably beyond its control, including but not limited to the failure or breakdown of generating or transmitting facilities, floods, fire, strikes, or action or order of any agency having jurisdiction in the premises, or for interruptions which are necessary for inspection, repair or changes in the distribution system of the city. (2) The customer shall notify the city immediately of any defects, trouble or accident which may in any way affect the delivery of power by the city to the customer.

(Code 1981, § 29-28(A)(II)(b); Ord. No. 2001-46, § 3, 6-25-2001; Ord. No. 2002-36, § 3, 6-24-2002; Ord. No. 2003-35, § 3, 6-23-2003; Ord. No. 2004-26, § 3, 6-28-2004; Ord. No. 2005-29, § 3, 6-27-2005; Ord. No. 2006-35, § 3, 6-26-2006; Ord. No. 2007-32, § 3, 6-25-2007; Ord. No. 2008-28, § 3, 6-23-2008; Ord. No. 2009-23, § 3, 6-22-2009; Ord. No. 2010-29, § 3, 6-28-2010; Ord. No. 2011-19, § 3, 6-27-2011; Ord. No. 2012-27, § 3, 6-25-2012; Ord. No. 2013-25, § 3, 6-24-2013; Ord. No. 2014-30, § 3, 6-23-2014; Ord. No. 2015-24, § 3, 6-22-2015; Ord. No. 2016-36, § 3, 6-27-2016; Ord. No. 2021-7, § 3(Exh. A), 2-8-2021, eff. 2-1-2021; Ord. No. 2024-38, § 3, 6-24-2024; Ord. No. 2025-27, § 3(Exh. A), 6-23-2025)