1300.8. - Pre-Filtration and First-Flush Diverters.
(a) All potable rainwater catchment systems shall be fitted with a pre-filtration device. It is recommended that pre-filter screens are a maximum of one-thirty-second inch. The screen should be washed clean of debris after each rain event. (b) All potable rainwater catchment systems shall have a first-flush diverter installed in a manner which will divert the first flow of water from the catchment surface. First-flush diverters shall be installed after the pre-filtration device. (c) Water drained from the first-flush diverter will be piped away from the storage tank and terminate in a location which will not cause damage to property or erosion. (d) First-flush diverters shall be sized so that the minimum volume of the water diverted is at least equal to one gallon (3.8L) per each 100 square foot (9.3 m2) of catchment area served. (e) First-flush diverter vessels shall have a cleanout fitting in the bottom of the device. Cleanouts shall be removed and the accumulated debris washed out as per manufacturer recommendations. First-flush diverters shall be provided with an automatic means of self draining between rain events.
(Ord. No. 2011-43(11-O-0740), § 1, 9-28-11)
Ask a question about Atlanta law
Corpus searches the Atlanta sections it holds and shows the ones that match, with their citations. Free, no sign-in.